STOCK TITAN

AMEX Exploration Delivers Exceptional PEA on Perron Gold Project

Rhea-AI Impact
(Low)
Rhea-AI Sentiment
(Neutral)
Tags

Amex Exploration announces positive PEA results for its wholly-owned Perron gold project in Quebec. The project demonstrates strong economics with a pre-tax IRR of 59.5% and NPV of C$948 million at US$2,000/oz gold. The mine plan envisions a 10-year operation producing an average of 101,000 oz Au annually, with higher production of 124,000 oz Au in the first 5 years. Initial capital expenditure is estimated at C$229 million with all-in sustaining costs of US$807/oz Au. The project will utilize underground mining supplemented by open pit operations, processing 1,750 tonnes per day with a 95% gold recovery rate. Environmental impact is minimized by using mined-out pits for tailings storage.

Amex Exploration annuncia risultati positivi per la PEA del suo progetto aurifero Perron, interamente di proprietà, in Quebec. Il progetto dimostra solide economie con un IRR pre-tassa del 59,5% e un NPV di 948 milioni di CAD a un prezzo dell'oro di 2.000 USD/oz. Il piano minerario prevede un funzionamento di 10 anni con una produzione media di 101.000 oz Au all'anno, con una produzione più alta di 124.000 oz Au nei primi 5 anni. La spesa iniziale per i capitali è stimata in 229 milioni di CAD, con costi sostenuti totali di 807 USD/oz Au. Il progetto utilizzerà estrazione sotterranea integrata con operazioni a cielo aperto, elaborando 1.750 tonnellate al giorno con un tasso di recupero dell'oro del 95%. L'impatto ambientale è ridotto al minimo utilizzando le cave esaurite per lo stoccaggio delle scorie.

Amex Exploration anuncia resultados positivos de PEA para su proyecto de oro Perron, de propiedad total, en Quebec. El proyecto demuestra una sólida economía con un TAE pre-impuesto del 59,5% y un VAN de 948 millones de CAD a un precio del oro de 2.000 USD/oz. El plan minero prevé un funcionamiento de 10 años produciendo un promedio de 101.000 oz Au anualmente, con una producción mayor de 124.000 oz Au en los primeros 5 años. La inversión inicial de capital se estima en 229 millones de CAD, con costos sostenidos totales de 807 USD/oz Au. El proyecto utilizará minería subterránea complementada por operaciones a cielo abierto, procesando 1.750 toneladas por día con una tasa de recuperación de oro del 95%. El impacto ambiental se minimiza utilizando las minas agotadas para el almacenamiento de relaves.

Amex Exploration은 퀘벡에 있는 전액 소유의 페론 금 프로젝트에 대한 긍정적인 PEA 결과를 발표했습니다. 이 프로젝트는 2,000 USD/oz 금 가격에서 세전 내부수익률(IRR) 59.5%NPV 9억 4,800만 CAD라는 강력한 경제성을 보여줍니다. 광산 계획은 연평균 101,000 oz Au를 생산하는 10년 운영을 구상하고 있으며, 처음 5년 동안은 더 높은 생산량인 124,000 oz Au를 예상하고 있습니다. 초기 자본 지출은 2억 2,900만 CAD로 추정되며, 총 유지비용은 807 USD/oz Au입니다. 이 프로젝트는 1,750톤을 처리하고 95%의 금 회수율을 달성하면서 지하 채굴과 개방형 작업을 결합할 것입니다. 환경 영향은 고갈된 채굴 구역을 폐기물 저장소로 사용하는 방법으로 최소화됩니다.

Amex Exploration annonce des résultats positifs pour l'étude de préfaisabilité (PEA) de son projet aurifère Perron, entièrement détenu, au Québec. Le projet présente de solides résultats économiques avec un TIR avant impôt de 59,5% et une VAN de 948 millions CAD à un prix de l'or de 2 000 USD/oz. Le plan minier envisage une exploitation sur 10 ans produisant en moyenne 101 000 oz Au par an, avec une production plus élevée de 124 000 oz Au au cours des 5 premières années. Les dépenses en capital initiales sont estimées à 229 millions CAD, avec des coûts soutenus de 807 USD/oz Au. Le projet utilisera une extraction souterraine complétée par des opérations à ciel ouvert, traitant 1 750 tonnes par jour avec un taux de récupération de l'or de 95%. L'impact environnemental est minimisé en utilisant les fosses épuisées pour le stockage des résidus.

Amex Exploration gibt positive PEA-Ergebnisse für sein voll im Besitz befindliches Goldprojekt Perron in Quebec bekannt. Das Projekt zeigt starke wirtschaftliche Kennzahlen mit einem pre-tax IRR von 59,5% und einem NPV von 948 Millionen CAD bei einem Goldpreis von 2.000 USD/oz. Der Minenplan sieht eine 10-jährige Betriebszeit mit einer durchschnittlichen Produktion von 101.000 oz Au jährlich vor, wobei in den ersten 5 Jahren eine höhere Produktion von 124.000 oz Au angestrebt wird. Die anfänglichen Investitionskosten werden auf 229 Millionen CAD geschätzt, während die Gesamtkosten bei 807 USD/oz Au liegen. Das Projekt wird unterirdische Bergbaumethoden in Kombination mit Tagebau einsetzen und 1.750 Tonnen pro Tag mit einer Goldausbeute von 95% verarbeiten. Die Umweltbelastung wird durch die Nutzung von ausgebeuteten Gruben zur Lagerung von Abraum minimiert.

Positive
  • High IRR of 59.5% pre-tax and 40.2% after-tax
  • Strong NPV of C$948M pre-tax and C$525M after-tax
  • Low AISC of US$807/oz Au (US$739/oz first 5 years)
  • Quick payback period of 1.8 years after-tax
  • High-grade operation with 5.26 g/t Au average grade
  • Strong gold recovery rate of 95%
  • No environmental assessment required due to production below 2,000 tpd threshold
Negative
  • Significant initial capital requirement of C$229M
  • High sustaining capital costs of C$238M over LOM
  • Production decline after year 5 from 124,000 oz to 101,000 oz annual average
  • Pre-Tax IRR 59.5% and NPV C$948 M at US$2,000/oz Au
  • Average Annual production of 124,000 oz Au, for years 1 to 5 over a 10-year LOM
  • Cumulative Undiscounted Pre-Tax Cash Flow of C$1,333 M

Montreal, Quebec--(Newsfile Corp. - November 13, 2024) - Amex Exploration Inc. (TSXV: AMX) (FSE: MX0) (OTCQX: AMXEF) ("Amex" or the "Company") is pleased to announce the results of the NI 43-101 compliant Preliminary Economic Assessment (the "PEA") for its wholly-owned Perron gold project (the "Project"), located near the town of Normétal in the province of Quebec, Canada. The PEA was prepared in collaboration with independent engineering and geological firms Evomine, Bumigeme, Alphard, GoldMinds and Laurentia Exploration.

PEA Technical Presentation details

In connection with this news release, AMEX will hold a conference call and audio webcast on November 13, 2024, at 10 am EDT, followed by a question-and-answer session.

To access the call please register here:
https://us02web.zoom.us/webinar/register/WN_0Yr91YVLSOeYZJKt1Fbmpg#/registration

You may also access the conference call on a listen-only basis via webcast at our website www.amexexploration.com. The audio webcast will be archived on www.amexexploration.com.

All dollar ($) amounts in this news release are in Canadian dollar ($) unless otherwise indicated.

Perron Preliminary Economic Assessment Highlights:

The following assumes a gold price of US$2,000/ounce ("oz") and a C$/US$ exchange rate of 1.35:1.

  • 1,750 tonnes per day ("tpd") production rate with a Life-Of-Mine ("LOM") of 10 years;
  • Average diluted grades for gold ("Au") at 5.26 grams per tonne ("gpt");
    • Years 1 to 5: average diluted grade at 6.49 gpt Au.
  • Average annual production of 101,000 oz Au, or 1,014,000 million oz Au over LOM;
    • Years 1 to 5: average annual production of 124,000 oz Au (620,000 oz Au).
  • LOM All-in sustaining cash costs ("AISC") of US$807/oz Au;
    • Years 1 to 5: AISC of US$739/oz Au.
  • Initial Capital Expenditure ("Capex") of $229 million;
  • LOM Sustaining Capex of $230 million;
  • Pre-tax IRR of 59.5% and After-tax IRR of 40.2%;
  • Pre-tax NPV of $948 million and After-tax NPV of $525 million;
  • Cumulative Pre-tax Undiscounted Net Free Cash Flow of $1,333 million and Cumulative After-tax Undiscounted Net Free Cash Flow of $767 million; and
  • Pre-tax payback period of 1.5 years and After-tax payback period of 1.8.

CEO Commentary:

"This PEA marks an important milestone for AMEX and reaffirms our view that our fully owned Perron Project is a high-quality asset and has the potential of being a highly profitable stand-alone mining operation with minimal environmental impact" said Victor Cantore, President and Chief Executive Officer of AMEX Exploration. "The Project represents a strong combination of high-margin production and modest capital requirements, with the opportunity for significant resource growth in the future."

"This PEA demonstrates Perron's early potential based on a database close date of June 30th, 2024. Since the closing of the database, drilling has continued at depth and laterally and has already shown excellent high-grade intercepts beyond the currently defined mineral resource. This successful additional drilling demonstrates the continuation of mineralization and the upside potential for further resource and mine life additions in the future as we progress exploration."

Table 1: PEA Study Economic Analysis Highlights

ECONOMIC ANALYSIS HIGHLIGHTSBase CaseSpot
Gold PriceUS$/Au oz 2,000 2,600
Exchange RateC$/US$ 1.35 1.39
Pre-Tax Free Cash FlowCA$M 1,333 2,242
Pre-Tax NPV (5%)CA$M 948 1,625
Pre-Tax IRR% 59.5 87.5
Pre-Tax Payback PeriodYears 1.5 0.5
Ratio Pre-Tax NPV (5%) to CAPEXCA$M/CA$M 4.1 7.8
After-Tax Free Cash FlowCA$M 767 1,289
After-Tax NPV (5%)CA$M 525 914
After-Tax IRR% 40.2 59.7
After-Tax Payback PeriodYears 1.8 1.2
Ratio After-Tax NPV (5%) to CAPEXCA$M/CA$M 2.3 4.4

 

Table 2: PEA Physical Highlights

PHYSICAL HIGHLIGHTS
Annual Production - First 5 Years AverageOz/year124,000
Annual Production - Life-of-mine AverageOz/year101,000
Life-of-Mine ProductionOz1,014,000
Mill Processing Ratetpd1,750
Life-of-Mine Tonnes Processedkt6,316
Average Grade Processed - First 5 yearsAu gpt 6.49
Average Grade Processed - Life-of-MineAu gpt 5.26
Mine LifeYears 10
Average Processing Recovery Rate% 95.0

 

Table 3: PEA Study Financial Highlights

FINANCIAL HIGHLIGHTS
Average Operating CostUS$/Au oz 633
Average All-in Sustaining Cost ("AISC")US$/Au oz 807
Total Initial Capital ExpendituresxCA$M 229
Total Sustaining Capital ExpendituresCA$M 238

 

*Inclusive of gold sales net of royalty ($62M) in pre-production period

  1. The PEA is preliminary in nature and is based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too geologically speculative to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that the economic forecasts on which the PEA is based will be realized.
  2. The economic analysis of the project was carried out using a discounted cash flow approach on a pre-tax and after-tax basis with a discount rate of 5%.
  3. Revenue was based on a long-term gold price of $2,000/oz in USD.
  4. Cost estimates were prepared in C$.
  5. An exchange rate of 0.74 USD per 1.00 CAD was assumed.
  • Underpinned by world class infrastructure, the Perron PEA demonstrates a top-tier high margin gold mining operation in the stable jurisdiction of Quebec, Canada. The Project is located within the prolific Abitibi region, one of the most prolific gold belts in the world.

  • The PEA results confirm that Perron has the potential to be a stand-alone and highly profitable operation with an excellent internal rate of return (IRR) and after-tax net present value (NPV) at a range of gold prices.

  • The PEA shows that Perron has the potential to be a mine with limited environmental impact, utilizing the mined out open pits to store tailings and therefore avoiding the construction of a tailings management facility.

Mining

The mine will be operated as a mechanized underground operation, which will be complemented by open pit production. The mine will have an overall average production rate of 1,750 tpd of mineralized material over a 10-year production period that is preceded by a 2-year pre-production period.

The selected underground mining method is longitudinal longhole stoping with cemented rockfill. Stope dimensions average 17.5 m in length, 25 m in height, and 5.7 m in width (LOM average) with a minimum mining width of 3.0 m. The different sectors of the mine will be accessed via ramps and drifts to allow the efficient circulation of mobile mining equipment and to satisfy ventilation and emergency egress requirements. Mineralized material will be extracted using a fleet of owner-operated equipment that includes 10 tonne LHDs and 42 tonne haul trucks.

Five open pits are included in the mine plan and utilize conventional truck and shovel mining that will be executed by a contractor. The pits will begin to be mined in the preproduction period, with material completely extracted by year 4 as they are sequenced such that they can be used to manage all tailings generated by the mill.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_002.jpg

Figure 1: Mine Design

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_002full.jpg

Table 4: Mine Physicals



TotalYr -2Yr -1Yr 1Yr 2Yr 3Yr 4Yr 5Yr 6Yr 7Yr 8Yr 9Yr 10
Mineralized material mined - Undergroundkt5,6538181492343503462653656653651654398
Waste rock mined - Undergroundkt2,94815133630229026132029926425320322445
Subtotal - Undergroundkt8,601159517794633764782952920906855878443
Mineralized material mined - Open pitkt663858511833148193000000
Waste rock mined - Open pitkt6,2718681,3026728681,4611,101000000
Overburden mined - Open pitkt2,878691409789924650000000
Subtotal - Open pitkt9,8121,6441,7961,5791,8251,6731,295000000
Strip ratio - Open pit-13.818.320.112.353.910.35.70.00.00.00.00.00.0
Total miningkt18,4131,8032,3132,3732,4582,4382,077952920906855878443

 

Processing

A total of 1,750 tpd of material will be processed in a plant that consists of primary crushing, followed by a grinding circuit consisting of a semi-autogenous grinding mill of 5.5 m diameter x 1.8 m long in an opened circuit and a ball mill of 4.0 m diameter x 6.7 m long in a closed circuit with cyclones - SABC circuit. A gravity circuit followed by leaching will recover coarse gold from the cyclone underflow, while the cyclone overflow, at a P80=74 microns, is treated in a six (6) tank carbon-in-leach circuit, followed by SO2/air cyanide destruction. Gold will be recovered in an adsorption-desorption-recovery circuit and electrowinning cells, with gold room recovery and production of bullion bars.

The CIL tailings after the cyanide destruction will be pumped to a high-rate thickener to increase the slurry density to 62-64 % solid and pumped to empty pits.

The process plant gold recovery is estimated to average 95.0% over the LOM.

The process plant building will include a laboratory, mill offices, a dry and an electrical and mechanical shop.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_003.jpg

Figure 2: Flowsheet

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_003full.jpg

Table 5: Gold Production by Source





Pre-productionProduction



TotalYr -2Yr -1Yr 1Yr 2Yr 3Yr 4Yr 5Yr 6Yr 7Yr 8Yr 9Yr 10
Stockpiles
(OP & UG)
Mill Feedkt531 - 46 113 250 4
1 - 2 4 - 112
GradeAu gpt3.00 - 4.73 3.92 1.83 1.51 2.02 6.68 - 5.95 5.28 - 3.87
Gold recoveredAu koz49 - 7 13 14


-
1 - 13
Open pitMill Feedkt340 - - 1 28 133 178 - - - - - -
GradeAu gpt1.91 - - 2.13 1.27 1.72 2.16 - - - - - -
Gold recoveredAu koz20 - - 0 1 7 12 - - - - - -
UndergroundMill Feedkt5,445 - 75 486 343 503 461 638 639 638 635 639 389
GradeAu gpt5.68 - 7.39 7.44 11.48 6.20 7.88 7.03 5.54 3.07 3.92 3.76 3.16
Gold recoveredAu koz945 - 17 110 120 95 111 137 108 60 76 73 38
CombinedMill Feedkt6,316 - 121 599 621 641 639 639 639 641 639 639 501
GradeAu gpt5.26 - 6.38 6.77 7.13 5.24 6.29 7.03 5.54 3.08 3.92 3.76 3.32
Gold recoveredAu koz1,014 - 24 124 135 103 123 137 108 60 77 73 51

 

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_004.jpg

Figure 3: Gold Production

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_004full.jpg

Infrastructure

The Project is approximately 5 kilometers from the town of Normétal, Quebec and is accessible via a well-maintained forestry road. The Project will require construction of the following supporting infrastructure items: 1,750 tpd process plant complex, offices, dry, maintenance shop and warehouse; gatehouse; 5 kilometers of 120kV transmission lines; 120 kV main substation; final effluent water treatment plant; surface water management facility, including ditches, pond and pumping stations; service and haulage roads; potable water and sewage systems; underground mine portal, mine ventilation systems (intake and exhaust) and waste dump and overburden storage facilities. No camp will be required considering the nearby qualified labor pool.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_005.jpg

Figure 4: Suggested Infrastructures Arrangement

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_005full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_006.jpg

Figure 5: General site arrangement

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_006full.jpg

Workforce

During the 18-month construction period of the mine, the workforce will peak at approximately 250 people, this is in addition to employees who would be required for open pit and underground mining and G&A.

During steady state operations, the average number of employees (mine, process plant and G&A) is estimated at 164 people, excluding contractors (open-pit mining, contract services, etc.).

Tailings

The tailings storage plan will take advantage of open pits that will be mined in the first half of the mine life. Process plant rejects will be thickened and pumped to the mined-out pits sequentially for permanent storage. Tailings will then consolidate over time and excess water will either be used for processing requirements or discharged to the environment once quality conditions are met. This concept aims to limit the environmental impact of the Perron Project, to limit the risks related to traditional Tailings Management Facility (TMF) stability, to simplify short-term and long-term monitoring and to greatly reduce the capital and operating costs related to tailings management.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_007.jpg

Figure 6: Visual of in-pit tailings disposal

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_007full.jpg

Capital Expenditure

The total initial construction capital expenditure ("CAPEX") is forecasted at $229M after accounting for $62M in gold sales revenues (pre-production credits). Capitalized mine development prior to commercial production is expected to be approximately $112M, comprised of $38M related to open pit mining and $74M related to underground mining. The majority of the capitalized open pit mining is driven by the strategic decision to complete the mining of a small open pit in the pre-production period in order to be able to start disposing tailings at the commissioning of the process plant. The construction capital accounts for the site development, water treatment and infrastructure area including a truck shop, warehouse and an administration facility. Additionally, the capital estimate includes $15.1M of EPCM and indirect costs and a contingency of $25M.

Quotations from reputable suppliers were obtained for most of the large and high-cost equipment required for the plant, mine and site infrastructure. For other equipment and supplies, cost estimates were based on comparable projects, historical data or derived through consultants' in-house databases.

Table 6: Capital Expenditure

ItemCA$M
Site Preparation & Infrastructures16.6
Power & Electrical11.2
Water & Tailings Management10.3
Process Plant58.0
EPCM / Indirects15.1
Contingency25.0
Subtotal136.2
Preproduction, Startup & Commissioning131.3
Mobile Equipment (*quotations received)23.3
Subtotal290.8
Less: Pre-Prod. Credit (Gold Sales) net of TC/RX & Royalties-62.1
Total228.7

 

The sustaining capex ("SUSEX") is estimated to be $238M, including $8M of closure and rehabilitation costs. Underground mining SUSEX is earmarked for mining development, additional equipment, replacement units, and major repairs. Other sustaining capex captures in-pits tailings storage, infrastructures and G&A.

Table 7: Sustaining Capital Expenditure

ItemLOM Total
(CA$M)
Avg. LOM
(US$/Au oz)
Underground & Others229.8 167.8
Closure and Rehabilitation7.8 5.7
Total237.6 173.6

 

Operating Costs

Life of Mine (LOM) total operating cost is estimated at US$633 per ounce of gold produced, as summarized below. The LOM total AISC is estimated to be US$807 per ounce of gold produced based on average annual gold production of 101,000 ounces over the 10 years of mine life. This cost structure places the Project in the bottom quartile of the global gold cost curve, which is mostly due to the high-grade nature of the mineralized material and to the simplicity of mining.

Table 8: Operating Costs

ItemLOM Total
(CA$M)
Avg. LOM
(CA$/t milled)
Avg. LOM
(US$/Au oz)
Mining Costs (Open pit + underground)536.7 84.97 394
Processing163.0 25.81 120
General & Administration116.7 18.47 86
Offsite Costs5.5 0.87 4
Royalty (1.5%)39.8 6.31 29
Total Operating Costs861.7 136.42 633
Sustaining Capital Expenditure237.6 37.62 174
All-in Sustaining Capital ("AISC")1,099.3 174.04 807

 

Financial Analysis

At base case gold price of US$2,000/oz and exchange rate of 1.35, the Project generates after-tax Net Present Value ("NPV") of $525M using 5% discount rate and an after-tax Internal Rate of Return ("IRR") of 40.2% with a payback period of 1.8 years from the commencement of commercial production. The Project generates cumulative free cash flow of $767M and average annual free cash flow of $100M over the 10 years production period. Total taxes payable over LOM at the base case gold price is $566M.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_008.jpg

Figure 7: After-Tax FCF

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_008full.jpg

The PEA financial economic analysis is significantly influenced by gold prices. At spot prices of US$2,600/Au oz and exchange rate of 1.39, the Project generates an after-tax NPV of $914M and an after-tax IRR of 59.7% with a payback period of 1.2 years. A sensitivity analysis was performed on the gold price, CAPEX, overall OPEX and exchange rate.

Table 9 & 10: Sensitivity Analysis on NPV (5%) and IRR

Gold PriceAfter-Tax NPV
(5%) (CA$M)
Initial CAPEXTotal OPEXFX
US$/Au ozBase Case -20%+20%-20%+20%-20%+20%
1,50023128617530015743407
1,750379432325447310171582
2,000525576473591457290755
2,250669719619735603408927
2,5008138617648777475251,097
2,7509561,0029081,0208916411,267
3,0001,0981,1431,0521,1611,0347561,437








Gold PriceAfter-Tax IRRInitial CAPEXTotal OPEXFX
US$/Au ozBase Case-20%+20%-20%+20%-20%+20%
1,50022.8%30.6%16.9%26.8%18.1%8.9%33.7%
1,75032.0%40.7%25.5%35.4%28.3%18.7%43.3%
2,00040.2%49.7%33.1%43.2%37.0%26.6%52.1%
2,25047.8%58.0%40.1%50.5%44.9%33.7%60.3%
2,50054.9%65.8%46.7%57.4%52.3%40.2%68.1%
2,75061.7%73.2%53.0%64.0%59.3%46.3%75.6%
3,00068.2%80.4%59.0%70.4%65.9%52.1%82.9%

 

Permitting and Environment

The opening and operation of a mine that has a production capacity equal to or less than 2,000 tonnes per day is not subjected to an environmental impact assessment ("EIA") according to chapter Q-2 of the Environmental Quality Act ("EQA") for the emission of a ministerial decree. As modelled in the PEA, the Perron Project would therefore not submit to processes of and EIA and to the Bureau d'audiences publiques sur l'environnement (''BAPE''), as per current regulation, as the estimated production of 1,750 tonnes per day is below the threshold. However, an application for a ministerial authorization will need to be submitted to the Ministère de l'Environnement, de la Lutte contre les changements climatiques, de la Faune et des Parcs (''MELCCFP''). Studies will be required as part of this application including, hydrological studies, hydrogeological and geochemical analysis, soil quality analysis, surface water, groundwater and sediment quality, characterization of the natural environment, including water bodies, wetlands, species with special status and wildlife inventories for certain species.

The acquisition of baseline environmental knowledge on the Perron property began several years ago and is still ongoing today. An environmental scoping study has been carried out, and to date, no major environmental issues have been identified in the work undertaken. Additional environmental work is planned to be carried out in 2025 such as a geochemical characterization program, various environmental inventories and social engagement with the local stakeholders.

Stakeholder Engagement

The aboriginal community concerned by Amex's activities is the Abitibiwinni First Nation which is an Algonquin First Nation residing primarily in the community of Pikogan in the Abitibi-Temiscamingue region. The Pikogan community, also called Abitibiwinni, is located three (3) kilometers from the town of Amos on the west bank of the Harricana River. The Perron project is located on a part of the ancestral territory of the Algonquin Anishinabeg Nation. A relationship of trust and respect has been built with the Abitibiwinni First Nation Council over the years by demonstrating transparency and consideration. With respect to local communities near the project, Normétal, Valcanton and Saint-Lambert are the main municipalities surrounding the Perron project.

Amex has always prioritized engaging stakeholders and implementing communication and consultation plans. Communication plans include a summary of the work completed on the property every six months as well as the company's orientations for the coming months.

Active participation in the communities through sponsorship, investment, etc. is part of AMEX's core values and aids in fostering good long-term relationships. AMEX will continue consulting, supporting and informing all stakeholders at all stages of the project development.

Exploration Update

The PEA was based upon the Mineral Resource Estimate ("MRE") for which the drill database was closed on June 30, 2024 (please see press release dated September 5, 2024). Since this date, Amex has drilled approximately a further 28,000 m on the Perron Property. This drilling has been demonstrating the growth potential that exists across several zones at Perron.

The Company has displayed in recent months that the High Grade Zone ("HGZ") is open not only at depth but also remains open in certain areas close to surface. The Denise Zone has fantastic potential for expansion in multiple directions, which is significant given its proximity to the HGZ. The latest press release (dated November 6, 2024) showed the growth potential of several zones and that exceptionally high-grade gold can be found across the entirety of the Perron Property.

Since obtaining the MRE, the Amex Exploration team has been optimizing drill planning to target expansion of the open pit and underground stope shapes identified in the resource. Numerous areas across the project have been outlined for expansion due to a lack of drilling. With the PEA now in hand, drill planning will be further refined to prioritize the growth of economic ounces and importantly identify where additional tonnage can be added to the earlier years of the mine life to further enhance the mine's optimization.

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_009.jpg

Figure 8: Example (from the HGZ) to display that drilling completed after the database cutoff of June 30, 2024 has the potential to add economic stopes to the existing resource (Assays from PE-24-797 fall outside current PEA stopes)

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_009full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_010.jpg

Figure 9: Additional example of high-grade gold intercepted in drilling completed after the database cutoff that holds the potential to significantly expand upon the existing defined resource (from CPZ-Grey Cat-Gratien area)

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/2667/229753_180e0785949a581c_010full.jpg

Mineral Resource Estimate

The Perron Project hosts mineral resources as detailed in the NI 43-101 compliant Mineral Resource Estimate with an effective date of September 5, 2024, which can be found on SEDAR+. The mineral resources that have flowed to the mine plan are contained within five different zones (High Grade, Denise, Gratien, Grey Cat and Team) over a strike length of 2,900 meters and span from surface to a depth of approximately 1,400 meters. Each zone is characterized by multiple tabular panels, which mainly trend ENE and dip vertically to sub-vertically.

Table 11: Summary of Mineral Resources

All ZonesOpen Pit Constrained UG stopes Total
COG 0.42 Au g/t COG 1.29 Au g/t
Tonnes Au gpt Au oz. Tonnes Au gpt Au oz. Tonnes Au gpt Au oz.
Measured131,2401.405,890445,2506.6094,530576,4905.42100,420
Indicated706,6001.8040,7803,030,6004.65452,9303,737,2004.11493,710
Indicated+Measured837,8401.7346,6703,475,8504.90547,4604,313,6904.28594,130
Inferred996,4702.0164,4207 597 2804.03985,2408,593,7503.801,049,660

 

  1. The mineral resource estimate is compliant with CIM 2019 standards and guidelines for reporting mineral resources and reserves.
  2. Resources are presented undiluted and in situ and are considered to have reasonable prospects for economic extraction. The resources at surface are constrained by pit optimization surfaces and the underground resources are constrained by mineable shapes.
  3. The database comprised a total of 1,533 drill holes for 547,361 metres of drilling (which includes historical drilling completed by previous operators) in the extent of the mineral resource, of which (312,051.20 metres) 264,462 samples were assayed as of June 30th, 2024, grid spacing are variable (The Genesis file is Amex_24 Aout 2024_MR.gnft and where the database file is BD_AMEX_08 Jul 2024_MR.accdb).
  4. All NQ core assays reported by AMEX were obtained by analytical methods described below under "QA&QC".
  5. Geological interpretation of the deposits was based on lithologies, mineralized zones orientation and the mineral observations. Each zone has its own characteristic of mineral occurrence and amount of free gold.
  6. Interpretation was initially made from cross-sections at intervals, and then completed in GENESIS, a modelling software, where selections of mineralization intervals were combined to generate mineralization wireframes. Envelopes are generally subvertical with various plunges.
  7. The mineral resource estimate encompasses a total of 189 envelopes, sub-vertical gold-bearing envelopes/domains each defined by individual wireframes with a minimum true thickness of 2.0 metres.
  8. Samples were composited within the mineralization envelopes into 1.0 metre length composites. A value of zero grade was applied in cases of core not assayed.
  9. High grade capping was done on composite data and established using a statistical analysis on a per-zone basis for gold. Capping varied from 5 g/t Au to 200 g/t Au and was applied on composites within each specific envelope.
  10. Density values were applied on the different mineralized zones (t/m3) varied from 2.67 to 2.83 from core measurement.
  11. Inverse distance squared grade estimation is used. The trial of Ordinary Kriging (OK) was rejected due to smearing and non-effective representation of high-grade areas.
  12. Most of the estimates are based on a block dimension of 2m North, 2m East and 2m height and estimation parameters determined by variography. The High-Grade zone has blocks of 2.5m East x 5m Z (Elevation) x 0.5m North.
  13. Estimates use metric units (metres, tonnes and g/t). Metal contents are presented in troy ounces (metric tonne x grade / 31.10348).
  14. GoldMinds is not aware of any known environmental, permitting, legal, title-related, taxation, socio-political or marketing issues, or any other relevant issue not reported in the technical report, that could materially affect the mineral resource estimate.

Qualified Persons

The qualified persons independent of the issuer, responsible for the technical information in this Press Release are Stephen Coates, P.Eng. of Evomine, Alexandre Burelle, P.Eng. of Evomine, Florent Baril, P.Eng. of Bumigeme, Claude Bissonnette, PMP, P.Eng. of Alphard, Pascale Pierre, Ph.D., P.Eng. of Alphard, Claude Duplessis P.Eng. of GoldMinds, Merouane Rachidi, Ph.D., P.Geo. of GoldMinds, and Jérôme Augustin, Ph.D., P.Geo. of Laurentia Exploration. They declare that they have read this press release and that the scientific and technical information relating to the resource estimate and preliminary economic assessment presented therein are correct.

Disclosure

Non-GAAP financial measures

The Company has included certain non-GAAP financial measures in this document. These financial measures are not defined under IFRS and should not be considered in isolation. The Company believes that these financial measures, together with financial measures determined in accordance with IFRS, provide investors with an improved ability to evaluate the underlying performance of the Company. The inclusion of these financial measures is meant to provide additional information and should not be used as a substitute for performance measures prepared in accordance with IFRS. These financial measures are not necessarily standard and therefore may not be comparable to other issuers.

All-in sustaining cost

All in sustaining cost is a non-GAAP financial measure calculated based on guidance published by the World Gold Council ("WGC"). The WGC is a market development organization for the gold industry and is an association whose membership comprises leading gold mining companies. Although the WGC is not a mining industry regulatory organization, it worked closely with its member companies to develop these metrics. Adoption of the all-in sustaining cost metric is voluntary and not necessarily standard, and therefore, this measure presented by the Company may not be comparable to similar measures presented by other issuers. The Company believes that the all-in sustaining cost measure complements existing measures and ratios reported.

All-in sustaining cost includes both operating and capital costs required to sustain gold production on an ongoing basis. Sustaining operating costs represent expenditures expected to be incurred that are considered necessary to maintain production. Sustaining capital represents expected capital expenditures comprising mine development costs, including capitalized waste, and ongoing replacement of mine equipment and other capital facilities, and does not include expected capital expenditures for major growth projects or enhancement capital for significant infrastructure improvements.

About Amex

Amex Exploration Inc. has made significant gold discoveries on its 100% owned high-grade Perron Gold Project located ~110 kilometres north of Rouyn-Noranda, Quebec, consisting of 117 contiguous claims covering 4,518 hectares. The project is well-serviced by existing infrastructure, on a year-round road, 10 minutes from an airport and just outside the town of Normétal (~8 km). In addition, the project is in close proximity to a number of major gold producers' milling operations. The project host both bulk tonnage and a high-grade gold style mineralization. Since January 2019, Amex has intersected significant gold mineralization in multiple gold zones and discovered copper-rich VMS zones.

For further information please contact:

Victor Cantore
President and Chief Executive Officer
Amex Exploration: +1-514-866-8209

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-looking statements

This news release contains forward-looking statements. All statements, other than of historical facts, that address activities, events or developments that the Company believes, expects or anticipates will or may occur in the future including, without limitation, the planned exploration program on the HGZ and Denise Zone, the expected positive exploration results, the extension of the mineralized zones, the timing of the exploration results, the ability of the Company to continue with the exploration program, the availability of the required funds to continue with the exploration and the potential mineralization or potential mineral resources are forward-looking statements. Forward-looking statements are generally identifiable by use of the words "will", "should", "continue", "expect", "anticipate", "estimate", "believe", "intend", "to earn", "to have', "plan" or "project" or the negative of these words or other variations on these words or comparable terminology. Forward-looking statements are subject to a number of risks and uncertainties, many of which are beyond the Company's ability to control or predict, that may cause the actual results of the Company to differ materially from those discussed in the forward-looking statements. Factors that could cause actual results or events to differ materially from current expectations include, among other things, failure to meet expected, estimated or planned exploration expenditures, failure to establish estimated mineral resources, the possibility that future exploration results will not be consistent with the Company's expectations, general business and economic conditions, changes in world gold markets, sufficient labour and equipment being available, changes in laws and permitting requirements, unanticipated weather changes, title disputes and claims, environmental risks as well as those risks identified in the Company's annual Management's Discussion and Analysis. Should one or more of these risks or uncertainties materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results may vary materially from those described and accordingly, readers should not place undue reliance on forward-looking statements. Although the Company has attempted to identify important risks, uncertainties and factors which could cause actual results to differ materially, there may be others that cause results not to be as anticipated, estimated or intended. The Company does not intend, and does not assume any obligation, to update these forward-looking statements except as otherwise required by applicable law.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/229753

FAQ

What is the expected annual gold production at Amex Exploration's Perron project (AMXEF)?

The Perron project expects average annual production of 124,000 oz gold for the first 5 years, and 101,000 oz gold over the 10-year life of mine.

What is the initial capital cost for Amex Exploration's Perron project (AMXEF)?

The initial capital expenditure (CAPEX) for the Perron project is C$229 million.

What is the all-in sustaining cost (AISC) for Amex Exploration's Perron project (AMXEF)?

The life-of-mine AISC is US$807 per ounce of gold, with years 1-5 having a lower AISC of US$739 per ounce.

What is the after-tax NPV and IRR for Amex Exploration's Perron project (AMXEF)?

The after-tax NPV (5% discount) is C$525 million with an IRR of 40.2% at US$2,000/oz gold price.

AMEX EXPLORATION INC ORD

OTC:AMXEF

AMXEF Rankings

AMXEF Latest News

AMXEF Stock Data

97.27M
82.34M
18.09%
6.88%
Gold
Basic Materials
Link
United States of America
Montreal