Amarillo receives regulatory approval for Posse power line
Amarillo Gold Corporation (TSXV: AGC, OTCQB: AGCBF) has announced the start of construction for a power line delivering electricity to its Posse Gold Mine after receiving final regulatory approval from Goiás State. The 67-kilometre, 138-kilovolt power line connects the mine to a substation in Porangatu, with an expected construction duration of 14 months. Approximately BRL50 million (US$9 million) is invested in the power supply project, which includes the line, a substation expansion, and temporary power sources during the build-out.
- Final regulatory approval received for power line construction.
- Investment of approximately BRL50 million (US$9 million) enhances energy infrastructure.
- Partnership with Enel Brasil strengthens project sustainability.
- None.
TORONTO, Oct. 25, 2021 (GLOBE NEWSWIRE) -- Construction can begin on a power line that will deliver electricity to the Posse Gold Mine, said Amarillo Gold Corporation (TSXV: AGC, OTCQB: AGCBF) today, after receiving the License to Install for the line from the State Secretariat for the Environment and Sustainable Development of Goiás State (SEMAD).
It was the final regulatory approval needed for the 67-kilometre 138-kilovolt power line that will cross three municipalities and connect the Company’s flagship Posse mine to a substation in Porangatu. Construction on the line is expected to start later this year and take about 14 months. An LI to expand the substation was previously received in February, and work on the expansion is now in its final phase.
Approximately BRL50 million (US
The power line and Porangatu substation expansion are being built through a partnership between Amarillo’s subsidiary Amarillo Mineração do Brasil and Enel Brasil, the state power utility. Enel has granted its approval of the overall project, and all the land for the power line has been acquired.
“Our goal from the beginning has been to build a power infrastructure that will meet the needs of the Posse Gold Mine and leave a valuable legacy to the community long after we’re gone,” said Paulo Serpa, Amarillo’s Country Manager. “Our partnership with Enel and these approvals show that we are making steady progress towards achieving this goal.”
In addition, Amarillo has received approval from SEMAD to divert an existing power line that otherwise would run through the planned pit area for the Posse Mine. The 69-kilovolt line provides power for the municipality.
A temporary power line will meet Amarillo’s energy needs during construction. The existing 34.5- and 13.8-kilovolt overhead power lines that serve small loads on land close to the Posse Project will be relocated. This work is expected to begin in November.
About Amarillo
Amarillo is advancing two gold projects located near excellent infrastructure in mining-friendly states in Brazil.
The development stage Posse Gold Project is on the Company’s Mara Rosa Property in Goiás State. It has a positive definitive feasibility study that shows it can be built into a profitable operation with low costs and a strong financial return. Mara Rosa also shows the potential for discovering additional near-surface deposits that will extend Posse’s mine life beyond its initial 10 years.
The exploration stage Lavras do Sul Project in Rio Grande do Sul State has more than 23 prospects centered on historic gold workings.
Amarillo trades on the TSXV under the symbol AGC and the OTCQB under the symbol AGCBF. Visit www.amarillogold.com to learn more about the Company’s focus on becoming a mid-tier Brazilian gold producer.
Follow us on LinkedIn, Twitter, and YouTube.
Contact information
Mike Mutchler
President & CEO
416-294-0736
mike.mutchler@amarillogold.com
Annemarie Brissenden
Investor Relations
416-844-6284
annemarie.brissenden@amarillogold.com
Marcelo Lins
Sócio Diretor, ML&A Comunicações
mlins@mla.com.br
(11) 3811-2827
NOTES
Neither the TSX Venture Exchange nor its Regulation Services Provider (as defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of the content of this news release.
Forward-looking statements
This news release contains forward-looking statements regarding the Company’s current expectations regarding future events, including its business, operations and condition, and management’s objectives, strategies, beliefs, and intentions.
Various factors may prevent or delay our plans, including but not limited to, the trading price of the common shares of the Company, capital market conditions, impacts from the coronavirus or other epidemics, counterparty risk, TSXV approval(s), contractor availability and performance, weather, access, mineral and gold prices, and success and failure of the exploration and development carried out at various stages of the program. Permission from the government and community is also required to proceed with future mining production. Readers should review the Company’s ongoing quarterly and annual filings, as well as any other additional documentation comprising the Company’s public disclosure record, for additional information on risks and uncertainties relating to these forward-looking statements.
Readers should also review the risk factors applicable to junior mining exploration companies generally to better understand the variety of risks that can affect the Company. The Company undertakes no obligation to update publicly or otherwise revise any Forward-looking statements whether as a result of new information or future events or otherwise, except as may be required by law.
PDF available: http://ml.globenewswire.com/Resource/Download/6ac8116c-0a5f-4425-833a-ace9e2cdc3e0
FAQ
What recent approval did Amarillo Gold Corporation receive for its Posse Gold Mine project?
How long is the power line being constructed for the Posse Gold Mine?
What is the investment amount for the power supply project related to AGCBF?
Who is partnering with Amarillo Gold on the power line project?